Set Project Baseline Process
Use the Set Project Baseline API process to set and verify the values for the contract budget accounts.
Process Settings
Below are the settings you must define for the Set Project Baseline API process.
Setting | Description | Sample Value |
---|---|---|
ProcessID |
This setting informs Cobra to run the Set Project Baseline process. |
SetProjectBaseline |
Project |
This setting refers to the project where you want to run the Set Project Baseline process. This setting is required. |
Demo Advanced |
LogTimePhasedChanges | This setting is required if the project audit is off. Use this setting to enable or disable the time-phased data logging of baseline changes for a project with regulatory requirements.
Use one of the following values:
|
1 |
LogLevel | Use this setting to indicate the level where budget changes are captured.
This option is required. Use one of the following values:
|
Control Account |
NegotiatedCost | This setting refers to the budgeted contract target cost value.
This setting is optional. |
2290000.00 |
AuthorizedUnpricedWork | This setting refers to the authorized unpriced work value.
This setting is optional. |
500.50 |
ContractCeiling | This setting refers to the Budgeted and Estimate at Complete Contract Ceiling value for the project.
This setting is optional. |
484000.00 |
ManagementReserve | This setting refers to the values debited from to increase the distributed budget.
This setting is optional. |
20000.00 |
Sample Script
Below is a sample script file for the Set Project Baseline API process.
[Process010]
ProcessID=SetProjectBaseline
Project=Demo Advanced
LogTimePhasedChanges=1
LogLevel=Control Account
NegotiatedCost=2290000.00
AuthorizedUnpricedWork=5000.50
ContractCeiling=484000.00
ManagementReserve=20000.00